Tempino – Plaju oil pipeline carried out in order to replace the old existing pipe that aged more than 70 years. Additionally, this pipeline also aims to secure the feed oil supply to the RU III Refinery, because the best way to transport the oil is through pipe considering its effectiveness, cost, HSE and social aspects.

 

1.Tempino Plaju

Construction of an oil pipeline Tempino -Plaju implemented in order to replace the existing pipe which has been outstanding for more than 70 years. In addition, this project also aims umtuk securing oil supplies (feed) to Refinery RU III where the transport of oil through the pipeline is the best mode of transport in terms of effectiveness, cost and HSE and social aspects.
Oil volume: 20,000 BOPD
Production Age: 10 years
Pipe length: 267 km
Large Pipe: 6 inches and 8 inches
Location: includes segments Tempino - Ramba, ie ranging from KM 265 to KM 3
On Stream: 2012

 

News

11
Agustus

Ministry of Energy and Mineral Resources to Support Urban Gas Network in East Java

The Energy and Mineral Resources Minister Ignasius Jonan specially inspected the urban gas network construction in Mojokerto Regency, East Java, on Sunday (11/08). The construction project is carried out by Pertamina. The visit was meant to see firsthand the progress of the project financed with APBN 2017 of Rp 37.8 billion.....


more detail
08
Agustus

Gresik-Semarang Pipeline to Supply Gas from JTB

Pertagas steps up completion of the open access Gresik-Semarang gas pipeline construction project so as to ensure energy supply in the island of Java. The 267 Km-long pipeline with a diameter of 28 inches stretching from Tambak Lorok, Semarang, Central Java, up to Gresik, East Java is expected to be completed in mid-2018.....